Capital Improvement Projects

Ivy Lift Station Upgrade
​
Scope of Work:
Replace the existing Ivy Lift Station with new wetwell and pumps
Reasons for Implementation:
1. Wetwell volume is too small
2. Lack of emergency power
Year of Implementation:
2018/2019
Estimated Cost:
$1,000,000
Target Year:
2020/2021
One Time or Continuous:
One Time
Picture
UPS Freight Emergency Power
​
Scope of Work:
Adding emergency power supply at UPS Freight Lift Station
Reasons for Implementation:
Lack of emergency power
Year of Implementation:
2018/2019
Estimated Cost:
$110,000
Target Year:
2020/2021
One Time or Continuous:
One Time
Picture
Mobile Power Generator
​
Scope of Work:
Portable power supply mounted on trailer
Reasons for Implementation:
Lack of emergency power
Year of Implementation:
2018/2019
Estimated Cost:
$25,000
Target Year:
2020/2021
One Time or Continuous:
One Time
SCADA System
​
Scope of Work:
Adding SCADA control system at all three lift stations
Reasons for Implementation:
Lack of operation data monitering
Year of Implementation:
2019/2020
Estimated Cost:
$45,000
Target Year:
2020/2021
One Time or Continuous:
One Time
Sewer Line CIPP
​
Scope of Work:
District-wide sewer line and manhole rehabilitation
Reasons for Implementation:
1. Reducing infiltration and inflow
​2. Routine maintenance

Year of Implementation:
2019/2020
Estimated Cost:
$1,165,300
Target Year:
2020/2021
One Time or Continuous:
One Time
Sewer Service Lateral Site Survey
​
Scope of Work:
Survey 91 service lateral from sewer main to ROW
Reasons for Implementation:
Utility investigation
Year of Implementation:
2019/2020
Estimated Cost:
$15,000
Target Year:
2020/2021
One Time or Continuous:
One Time
Employee Benefit Plan
​
Scope of Work:
Adding employee health insurance and pension plan
Reasons for Implementation:
Retain employees
Year of Implementation:
2019/2020
Estimated Cost:
$150,000
Target Year:
2020/2021
One Time or Continuous:
Continuous
Engineering
​
Scope of Work:
Adding engineering budget for planning, design, and operation
Reasons for Implementation:
Retain engineers
Year of Implementation:
2019/2020
Estimated Cost:
$35,000
Target Year:
2020/2021
One Time or Continuous:
Continuous
Emergency Reserve Funding
​
Scope of Work:
Reserving emergency funds for unforeseeable situations
Reasons for Implementation:
Emergency response
Year of Implementation:
2019/2020
Estimated Cost:
$500,000
Target Year:
2020/2021
One Time or Continuous:
Budget/Reserve

INdustrial Park Water and sanitation district

6625 E. 49th Ave.
​Commerce City, CO 80022
Phone: 303-287-1624
Fax: 303-287-4204
industrialparkwsd.org
  • About
  • Projects
  • Notifications
    • District Notifications
    • Messages
  • Resources
  • FAQs
  • Publications
    • Permit
    • Forms
    • Publications
  • Contact